Login
Facebook
16 September 2011
Scheduled Road Works Loch Awe

 The works scheduled to begin on 18th September 2011, are now re-programmed to commence on Tuesday 20th September 2011, due to an over-run on the works currently underway at Taynuilt.

The Out-of-Hours working approved for Bonawe Quarry will be adjusted to suit.

Iain,

As per the schedule below, the road closure and consequent material delivery of materials from Bonawe was due to restart on Sunday 18th but due to a delay on the current resurfacing works at Taynuilt this will not now happen until Tuesday 20th September.

I think the previous works at Connel went well with the last deliveries from Bonawe leaving before midnight; we will be doing our best to ensure that the next phase is as trouble free.

If there are any other changes I will be in touch.

 

Colin Morrison

Regional Production Manager

colin .morrison@breedonaggregates.com

Tel: 01631 565128

 

 

 

Dunbeg Quarry, Dunbeg, Oban, PA37 1PX

www.breedonaggregates.com

 


 

 

Click for Map
sitemap | cookie policy | privacy policy | accessibility statement